This site has moved! From now on, I won't be updating these pages. If you want to see my current progress, check out my new blog at Grey Lady.

Side Note: If you are looking for the public domain propeller design program originally discussed on the FlyRotary list, click here to download it.

I am building a Cozy MKIV aircraft. This plane is a 4-seater Rutan-derived canard pusher capable of over 200kts with a modified canard to eliminate stall possibilities. Plans are available for $500, and construction is composite (fiberglass+epoxy over foam cores). This type of construction is very flexible, and requires minimal tooling. Total airframe costs should run approximately $18,000, and I expect to spend approximately $20,000 on the engine and initial avionics stack, for a combined total of approximately $38,000.

I have also typed up my thoughts leading up to the decision to build an airplane, and my selection of the Cozy, if you are curious.

Are you a new builder? In addition to the chapter details below, I have also typed up a set of tips.

Build Log
Chapter DescriptionStatusEst. TimeAct. TimeEst. CostAct. Cost
0 Getting Started... All Over Again   Completed  90.0 hrs  88.5 hrs $ 11280.00 $ 18362.42 
1 Introduction   Completed  46.0 hrs  47.0 hrs $ 520.00 $ 524.50 
2 Bill of Materials   Completed  0.0 hrs  0.0 hrs $ 0.00 $ 0.00 
3 Education   Completed  15.0 hrs  15.2 hrs $ 149.00 $ 119.91 
4 Fuselage Bulkheads   Completed  26.0 hrs  44.8 hrs $ 500.00 $ 1769.77 
5 Fuselage Sides   Completed  30.0 hrs  34.5 hrs $ 263.20 $ 53.16 
6 Fuselage Assembly   Completed  56.0 hrs  80.2 hrs $ 189.50 $ 5.75 
7 Fuselage Exterior   Completed  79.0 hrs  62.8 hrs $ 183.85 $ 79.00 
8 Head Rest and Seat Belts   In Progress  8.0 hrs  14.5 hrs $ 518.70 $ 1864.46 
9 Main Gear and Landing Brake   In Progress  0.0 hrs  0.0 hrs $ 1453.30 $ 3121.67 
10 Canard   Completed  0.0 hrs  0.0 hrs $ 0.00 $ 1917.00 
11 Elevators   Completed  0.0 hrs  0.0 hrs $ 69.25 $ 3800.00 
12 Canard Installation   In Progress  0.5 hrs  0.0 hrs $ 2.05 $ 0.00 
13 Nose, Nose Gear, and Brakes   In Progress  85.0 hrs  120.5 hrs $ 1137.35 $ 2164.00 
14 Center Section Spar   Completed  8.0 hrs  18.0 hrs $ 388.60 $ 1400.00 
15 Firewall   In Progress  0.0 hrs  0.0 hrs $ 157.75 $ 0.00 
16 Control System   In Progress  0.0 hrs  0.0 hrs $ 381.80 $ 360.00 
17 Trim System   In Progress  0.0 hrs  0.0 hrs $ 65.20 $ 0.00 
18 Canopy and Turtleback   In Progress  20.0 hrs  30.2 hrs $ 494.55 $ 120.00 
19 Wings, Ailerons, and Wing Attach   Completed  4.0 hrs  108.2 hrs $ 1305.40 $ 6147.22 
20 Winglets and Rudders   Completed  0.0 hrs  0.0 hrs $ 130.15 $ 0.00 
21 Strakes, Fuel, and Baggage   In Progress  0.0 hrs  0.0 hrs $ 856.85 $ 0.00 
22 Electrical   In Progress  121.2 hrs  24.8 hrs $ 12510.00 $ 0.00 
23 Engine Installation   In Progress  0.0 hrs  0.0 hrs $ 9100.00 $ 0.00 
24 Covers and Fairings   In Progress  0.0 hrs  0.0 hrs $ 136.20 $ 0.00 
25 Finishing   In Progress  0.0 hrs  0.0 hrs $ 682.30 $ 0.00 
26 Upholstery   In Progress  0.0 hrs  0.0 hrs $ 0.00 $ 0.00 
27 Other Tasks   In Progress  0.0 hrs  11.5 hrs $ 0.00 $ 0.00 
Totals: 588.8 hrs 700.7 hrs$ 42475.00$ 41808.86

I also have been planning some modifications to the core plans. One of the most critical will be the installation of a rotary engine in place of the traditional Lycoming.

This site is entirely database-driven and will allow me to track my progress as well as time spent and costs for each step. As a result, I can do things like the following:

Start of Build:2004-01-19
Last Step Completed:2008-07-20
Days Worked:1643
Build Hours: 593.50
Avg. Hours/Day: 2.77
Days left to 2500 hours: 688.28
Est. Completion:11-25-2010

The table above is a bit misleading because it neglects the learning curve, a slow start, and putting the project on hold for nearly a year. My current hope is that I can complete the core of the aircraft by middle to the end of 2006, spend the winter addressing things like the electrical system and engine installation, then get flying in 2007.